The plans are drawn, the contracts have been let and we’re finally getting our hands dirty at our latest project in Watson Road, Mt Martha.
The excavation took 3 days, using 3 trucks dumping spoil from the site 20 kms away on a farm in Moorooduc. The size of the trucks was paramount, as the site is located behind an existing house.
Twenty truck loads of spoil were removed from site by our expert excavator Sam Shepherd, using laser levels to ensure accuracy.





[…] engaged an interior designer to manage the interior spaces in our latest Mt Martha project – The Gallery – we will now never go back to doing it all ourselves. Even though our last project won an […]